The applicant proposes the construction of a 1500 sf house in the Royal Anchorage subdivision (12-5-13). The applicant will connect to the newly constructed community wastewater system. The project required a minor stormwater project and received a permit from the Lake George Park Commission (5346-16-07). Stormwater management system consisted of (8) Storm-Tech chambers installed behind a retaining wall.
JOHNSON
Last Updated On:
Thursday, May 28, 2009
Project Summary
Waterkeeper Perspective
The Waterkeeper concerns included: the installation of an under-drain under the infiltration device which would discharge the infiltrated stormwater, location of stormwater for the driveway surface and clarify the details on the number of Storm-Tech chambers
Waterkeeper Comments
Next Meeting
Related Town
Waterkeeper Comments Document
Project Address
Royal Anchorage subdivision
Putnam, NY 12861
Please refer to the Waterkeeper comment letter to the Town of Putnam Planning Board May 2009.